First article inspection (FAI) is how engineering and quality agree that a new CNC revision is buildable, measurable, and ready for the next lot. On prototypes, FAI should be rigorous enough to catch drawing gaps — without forcing aerospace paperwork on a 5-piece plastic fixture that will change next week.
Below is what belongs in an FAI package, where a CMM fits, how a prototype FAI differs from a production first article, and when an FAI has to be repeated.
What a useful FAI package includes
- Ballooned drawing — every dimension and note is numbered, so each result traces back to the revision you ordered.
- Measured results for each ballooned characteristic, with the method used (hand tools, height gauge, optical or CMM).
- Material identification or a mill certificate when required.
- Finish and special-process records, such as anodizing, plating or heat treatment, when the drawing calls them out.
- Notes on fixturing, setup, or process risks found during machining.
JS Model can scale the package from a concise prototype FAI to a fuller production first article, including AS9102-style layouts when specified. Tell us which format your customer expects on the quality kickoff call or in the RFQ.
Where a CMM fits in an FAI
An FAI does not always need a CMM. Plain sizes such as lengths, diameters and step heights are measured quickly with calipers, micrometers and height gauges. A CMM earns its place when the drawing uses GD&T that hand tools cannot verify well:
- True position of hole patterns relative to datums
- Profile of a surface on curved or freeform features
- Flatness, perpendicularity or concentricity tied to a datum scheme
- Many features that must be reported in one coordinate system
For those features, a CMM report gives a 3D layout with the deviation of each measured point from nominal. JS Model provides ZEISS CMM reports when the RFQ requests a full 3D layout, and uses optical systems for non-contact checks of radii, angles and contours. Mark the characteristics that need CMM data, so probing time is quoted with the job. Our article on CMM inspection for CNC parts covers the report itself.
| Feature on the drawing | Typical FAI method |
|---|---|
| Lengths, widths, hole sizes | Calipers, micrometers, plug gauges |
| Step and boss heights | Height gauge on the plate |
| Threads | Thread gauges |
| Radii, angles, small contours | Optical measurement |
| True position, profile, datum GD&T | CMM |
Prototype FAI vs production FAI
Prototype FAI answers: “Can this geometry and tolerance be made and verified?” Production FAI answers: “Is the locked process ready to repeat?” If the design is still moving, keep the first package light, freeze the drawing, then run a production-intent FAI before raising quantity on CNC or sheet metal.
On prototype and small-batch lots, JS Model checks critical features on every part, so the first article is not the only measured piece. Larger runs use AQL sampling, which makes a clean production FAI more important before the quantity goes up.
Timing: when to request FAI
Request FAI at quote stage when:
- The part is a new PN or revision
- Your customer requires buyoff before the balance ships
- GD&T or material certs are contractually required
Adding FAI after the lot is already machined creates schedule risk — probes and paperwork need planning with the same lead time as metal.
When an FAI has to be repeated
An FAI approves one revision made one way. Plan a new or partial FAI when:
- The drawing revision changes a dimension, tolerance or note
- The material, finish or an outside process changes
- The part moves to a different machine, fixture, program or site
- Production has paused for a long time; AS9102 uses a two-year lapse as the trigger
A partial FAI re-measures only the characteristics affected by the change, which keeps repeat orders moving without losing traceability.
How FAI reduces later scrap
Most late failures come from ambiguous datums, missing finish notes, or tolerances that fight the process. A first-article review surfaces those issues while the batch is still small. Combine FAI with DFM notes so the second lot is cheaper, not just larger.
What changes after a failed first article
If FAI fails, the right next step is containment: stop the balance, document the gap, and decide whether to rework, remake, or revise the drawing. Skipping that conversation and “hoping the next five are fine” is how pilot lots become scrap lots.
JS Model treats a failed FAI as a process input — DFM note, fixture tweak, or tolerance discussion — before we restart. That is slower than shipping blind and far cheaper than discovering the issue at your customer’s dock.
Request a quote with FAI scope, read how ISO 9001:2015 process control supports the inspection plan, or see what we run in-house.